Philips Street Bridge Update:
The final contract documents have been signed for the fabrication. The fabricator has begun the manufacturing process of the top deck. The company has submitted their required shop drawings and field measurements. The fabrication is scheduled to be completed in March. As we get closer we can narrow down the delivery of the deck.
MassDOT has given their final approval of the entire project, we are moving forward with the procurement of the contractor for installation. We will update this project when there are additional changes or new developments.