How will this development affect the Town’ water and sewer systems? Do we have enough capacity to support this development?

When the Town was developing the State Hospital Master Reuse Plan and drafting new zoning for the hospital area, the Town retained Pare Corporation to develop a conceptual water and sewer infrastructure plan and to estimate water and sewer demand for a proposal envisioned by the master plan. Pare Corporation’s report and materials are available on the Town website

After Pare Corporation completed their conceptual study, the Town’s consulting engineer Environmental Partners provided a peer review of the water and sewer infrastructure. Environmental Partners also analyzed the water and sewer usage information generated by Pare to determine whether the Town had sufficient capacity to absorb the potential new water and sewer demand. Environmental Partners’ report is available on the Town website

Environmental Partners’ findings were that:

  • MSH development’s estimated peak day water demands of 0.114 MGD could be accommodated under current authorized limits provided that the Town continues to be proactive with its water conservation programs.
  • MSH development’s daily sewer flow of 96,910 GPD could be accommodated by the existing 8‐inch PVC sewer system from Hospital Road to West Mill Street based on the assumptions stated in the report. 

Trinity Financial is not relying on these reports but rather commissioned its own studies as part of its due diligence.   These studies will be shared with the Town and peer-reviewed by independent consultants retained by the Town.   The findings will be discussed in meetings with the Board of Water and Sewerage that are open to the public.  

 

Show All Answers

1. What is the status of the Medfield State Hospital redevelopment effort?
2. How can I find out more about the Medfield State Hospital and the proposed redevelopment?
3. Will Medfield residents take a vote on whether to approve the sale?
4. When is the Special Town Meeting?
5. What will we be voting on at Town Meeting?
6. What is the threshold needed to approve the proposed sale at the Town Meeting?
7. Will the proposed Land Disposition Agreement that the Town will sign with Trinity be available for review before the Special Town Meeting?
8. What is the Trinity Financial’s proposal? What type of housing is proposed?
9. What happened to the concept of including commercial space, stores and restaurants?
10. Are there any affordable housing units in the project?
11. What costs has the Town incurred since purchasing the Medfield State Hospital from the Commonwealth of Massachusetts? Has the Town generated revenue from leasing out the property?
12. What are the projected revenues and expenses (fiscal impact) to the Town if the property is developed in accordance with Trinity’s proposal?
13. What is the Trinity Financial’s proposed purchase price?
14. What kind of public access will there be if the sale is approved?
15. Is there a map of the parts of the MSH property proposed for disposition?
16. Will the North Field and trails remain open and be accessible to the public for both humans and canines?
17. How will people park and access the Overlook and trails?
18. How will this development affect the Town’ water and sewer systems? Do we have enough capacity to support this development?
19. How many units of housing will there be? Will they be rental apartments or ownership condos?
20. What is the largest and smallest unit type? (SF)
21. Will there be housing options reserved for seniors on site?
22. What about public access?